Anti corrosion flat coating

Anti corrosion flat coating

Detailed introduction

Scope of application:Suitable for electroplating plants, breweries, vinegar plants, battery plants, chemical plants, soy sauce plants, wastewater treatment tanks, acid-base neutralization tanks, chemical storage areas, etc
Coating characteristics:Resistant to strong acid and alkali, seawater, and salt spray            
Strong adhesion, wear-resistant, impact resistant, dust-proof
Corrosion resistance to various chemical media           
Sufficient flatness and decorative properties
TECHNICAL INDEXDrying time - surface drying: ≤ 4H
Drying time - practical: ≤ 24 hours
Pencil hardness: ≥ 2H
Impact resistance (500g steel ball): 50g'cm
Wear resistance (750g/500r): ≤ 0.03g
Compressive strength: ≤ Grade 1
Resistant to 60% acidity and alkalinity: no significant change for 7 days
31% salt tolerance: no significant change after 7 days
Resistant to 10% nitric acid: no significant change after 7 days
Resistant to 10% acetic acid: no significant change after 7 days
Resistant to 10% sodium oxide gas: no significant change after 7 days
Resistant to 10% ammonium fluoride: no significant change after 7 days
Resistant to gasoline 120 # #: No significant change after 7 days
Construction proceduresconstruction methodMain materials - auxiliary materialsReference amount
Plain groundDo a good job in waterproofing treatment

undercoatScrape and apply epoxy primerDS-30#About 0.15kg/m ²
screedScrape the mortar layer with medium coating and quartz sandDS-400- Quartz sand0.25-0.7kg/m²
Putty layerApply putty layer with intermediate coating and scrapingDS-4000.15kg/m2 once
top coatRoll coating anti-corrosion flat coating topcoatDS-8100.15kg-0.18/m2
After completion, the overall floor will be bright and clean, with uniform color and no hollowing

Construction proceduresCoating thickness: generally 1mm-3mm. If it exceeds 2mm, it needs to be sandblasted
Personnel can only enter after 24 hours of construction completion, and heavy pressure can only be applied after 72 hours. (Based on 25 * C, the low-temperature opening time needs to be moderately extended)